1.
General
Furnish and install as shown on the plans ____ one (1) Precision model
FPH____-_____ forced draft, gas fired vertical firetube boiler rated
at _____ boiler horsepower. Boiler shall be designed for a maximum
allowable working pressure of (15psi) (150psi) and shall deliver
_____lb/hr (F&A 212º F) of steam at ____ psi (up to 135 psi)
operating pressure. Boiler shall be completely factory assembled and
tested, with controls and trim as specified below. Complete package
shall be UL Listed and shall carry the Underwriters Laboratories
Listing Mark. Units rated at 9.5 boiler horsepower and over shall
also comply with ASME CSD-1. Boiler shall be designated for _____V,
_______PH, _______HZ electrical supply with single power connection.
2. Pressure Vessel
Vessel shall be constructed and stamped in accordance with ASME
Section IV (15 psi) or Section I (150 psi) and shall be registered
with the National Board. Shell and tubesheets shall be fabricated
from carbon steel. Tubes shall be 2” OD x 0.105 wall SA178A ERW
tubing. Vessel shall be stress relieved (units > 15psi design) and
equipped with inspection openings as required by ASME Code.
3. Combustion Chamber
Combustion chamber shall be fabricated from steel plate, lined with
ceramic fiber blanket. Combustion chamber wall and bottom shall be of
monolithic construction, formed from high temperature refractory, not
less than 4” thick.
4. Burner
Provide forced-draft, flame retention head burner to burn natural (LP)
gas with on-off (low-high-low or full modulation) firing rate
control. Burner shall be equipped to fire at a maximum input of
_____Btu/hr at an elevation of _____ ft. Blower motor shall be 3450
rpm design with motor starter (units over ¾ hp). Burner controls
shall conform to UL795 (and CSD-1, FM, IRI codes). For electrical
supplies other than 120V, the burner shall be equipped with a control
circuit transformer.
5. Boiler Controls
Boiler shall be provided with the following controls:
-
Properly sized ASME
safety valve(s) set at _____psig, manual drain valve and pressure
gauge with gauge cock.
-
Operating control
and manual reset high limit control with siphon manifold; high-low
modulating control (where appropriate)
-
Automatic reset,
float type primary water level control with water level gauge glass
and manual blowdown valve; probe type auxiliary water level control
with manual reset with pilot light.
-
Slow opening and
quick opening bottom blowdown valves (units > 100 psi).
6.
Packaging
Complete package shall be factory assembled and mounted on structural
channel support skid. All specified components are to be mounted,
piped and wired. Boiler shall be insulated with a minimum of 4 inches
of ¾ pound density fiberglass and housed in a rectangular, 16 gauge
enamel painted steel jacket. Jacket temperatures shall not exceed 130º
F during continued operation at high fire. Lifting lugs shall be
provided to allow rigging of package during installation.
7.
Quality Control
Complete packaged boiler shall be manufactured by Precision Boilers in
strict accordance with ASME Boiler and Pressure Vessel Code in an ISO
9002 quality system.